engineering and consulting

where we have gained our expertise

factory_ref

references

Poland
  • Combined Cycle Gas Turbine – Żerań   
  • Waste to Energy – Kraków   
  • Energy from waste – Poznań   
  • Wastewater treatment – Kujawy   
  • Waste incinerator plant – Szczecin   
  • Steel mill plant – Kraków   
  • Coal fired power plant – Kozienice    
 
United Kingdom
  • Energy Recovery Facility – Dunbar   
  • Energy from waste – Kemsley   
  • Waste to energy – Parc Adfer   
  • Energy from waste – Peterborough   
  • Waste to energy – Gloucester   
  • Energy recovery facility – Beddington  
  • Biomass Facility – Ridham Dock   
  • Energy recovery facility – Avonmouth   
  • Waste to energy – Earls Gate
 
Sweden
  • Biogas plant – Stockholm
  • Waste to energy – Stockholm  
  • Biomass plant – Borås   
  • Waste to energy – Högbytorp 
 
France 
  • Waste to energy – Troyes  
  • Waste recovery centre – Thiverval 
 
Others
  • Energy from waste – Belgrade, Serbia  
  • ESP for power plants – Turkey  
  • Waste to Energy – Sharjah, UAE 
case_study

case studies

Poland

Customer: 

POSCO E&C

Introduction/challenge:  

The EPC contractor was oblivious to the very strict local regulations and standards which had to be explained and then applied in the basic and detailed design of the E&I scope. Installation works were conducted at the same time as the design study.    

Solutions:   

We provided thorough consulting services on the Polish standards and regulations and worked in two locations  – our design office on construction site thus ensuring close cooperation of electrical designers, the installation contractor and the customer.   

Scope of design:  

  • specific calculations for connection to the public grid operator 
  • electrical design of MV power distribution system including measurement system, relays and protections settings, selection and design of MV inverters and harmonic analysis
  • electrical design of the LV power distribution system including relays and protection settings, selectivity, and design of LV inverters  
  • design and detail engineering of the Emergency Diesel Generator unit   
  • comprehensive design of cable trays, power cable calculations, preparation of cable schedules  
  • design of the earthing system for the entire plant  
  • site supervision during installation works 
  • as-built documentation

Customer: 

Termomechanica Ecologica  

Introduction/challenge: 

TME continued works and deliveries within the WtE plant as a replacement of the previous EPC Contractor who left the site.  Our challenge was to deliver E&I&C studies for the overall plant within a very tight schedule. The studies were supposed to include existing solutions and their adaptation to the new process requirements from TME.  

Solutions: 

The works were carried out in office and on site simultaneously together with site surveys. Our engineers supported the on-site installation teams and took part in commissioning and start-up.    

Scope of design:  

  • electrical design of MV power distribution system including  measurement system, calculation of relay settings, selection and  design of MV inverters, harmonic analysis  
  • electrical design of the LV power distribution system including in particular calculation of relay settings and selectivity
  • design and parametrisation of LV inverters  
  • design and detail engineering of the Emergency Diesel Generator unit  
  • comprehensive design of cable trays, power cable calculations  
  • preparation of cable schedules  
  • design of the earthing system for the entire plant   
  • as-built documentation  

Great Britain

Customer: 

Babcock Willcox Volund  

Introduction/challenge: 

We were faced with a challenge related to the relatively big step-up transformer, around 45 MVA, and low short-circuit power in system – there was a voltage drop in the MV network when switching on the transformer.  

Solutions: 

We used the pre-magnetisation system and magnetised the transformer core with a diesel generator. Thanks to this solution, the switching on of the entire facility was unnoticeable for the overall power system.    

Scope of design:  

  • complete electrical design of the entire plant and specific calculations for the connection to the public grid operator   
  • electrical design of the MV plant including 
    • step-up transformer
    • MV/LV transformers  
    • MV cables  
    • cable trenches  33 and 11kV switchgears 
  • preparation of specific calculations such as
    • pre-magnetisation system
    • load flow analysis  
    • short circuit calculation note  
    • voltage fluctuation assessment  
    • voltage unbalance assessment  
    • HV protection grading and setting studies including generator protection 
    • HV insulation coordination  
    • HV/MV protection study  
    • harmonics calculations
  • design of 3D cable routes including cable pulling cards   
    • design of 3D cable way support including mechanical calculation notes  
    • design of the earthing system  
    • design of communication, I&C and power cables  
    • preparation of cable loop diagrams  
    • design of LV equipment including 
      • LV switchgears and busbars between transformers and switchgears  
      • 110 VDC UPS units
      • UPS units  
      • AVR cabinet  
      • NER cabinet  
      • Emergency Diesel Generator  
      • Local control boxes    

Sweden

Customer: 

Serneke AB  

Introduction/challenge:   

The challenge was about conducting our scopes within the building information modeling standard (BIM).  

Solutions:  

We had to adjust the software used for 3D modeling.   

Scope of design:

Comprehensive design for the administration/civil works including HVAC, fire protection system, access control, lighting, emergency lighting, underground earthing system  

  • design of power supply cabinets  
  • design of the Ethernet system 
  • design of the lightning protection system  
  • design of a small power distribution system within plant  
  • design of the UPS system  
  • design of the anti-freezing and heat tracing system  
  • design and specification of cable ladders in 3D and 2D  
  • 3D design within BIM specifications  
  • preparation of cable schedules including calculation  

Customer: 

Steinmueller Babcock Environment  

Introduction/challenge:   

Electrical works were conducted at the same time as the design study. Implementing a detailed support material for cable raceways into the 3D model posed yet another challenge.  

Solutions:   

We had to adjust our lightning sphere visualisation and the software for 3D modeling with regards to supporting materials.  

Scope of design:  

  • engineering works of cable ladders and trays in 3D  
  • defining the Bill of Quantity for cable ladders  
  • preparation of cable schedule including calculation of power cables cross-section  
  • defining lengths for each cable connection  
  • design of cabinets: safety switches, local control boxes, lightning protection cabinets, maintenance sockets  
  • design of the earthing system  
  • design of the emergency lighting system  
  • technical assistance  on site
  • as-built documentation including 3D modelling

France

Customer: 

CNIM SA  

Introduction/challenge: 

The design had to be in line with the national French standards and regulations including the process areas, normal emergency lighting with socket boxes and distribution board.  

Solution: 

We had to improve our calculations methods with the new software pursuant to NF C15-100.  

Scope of design:  

  • preparation of the complete package of technical specification for installation materials including applicable standards for: cables, cable ladders, conduits, accessories, junction boxes, labels 
  • design of cable trays in 3D and 2D including design of supplementary steel structures  
  • preparation of power, I&C, communication, and earthing cable schedules  
  • design of false floor including detailed design of supporting arms and collisions with cable ladders  
  • preparation of terminal wiring diagrams 
  • design of the lighting system (normal and emergency) including calculations in Dialux 
  • specification of lighting fixtures and auxiliary equipment  
  • typical schematics of lighting fixtures  
  • as-built documentation  
  • technical site supervision during cable tray and cable installation works  
  • electrical design of LV switchgears  
  • engineering of LV busbars routing between MV/LV transformers and LV switchgears  
  • selectivity studies  
  • short circuit calculation notes  
  • engineering of IO cabinets  
  • engineering of local control boxes and safety switches  
  • engineering of UPS system  
  • harmonic distortion studies   

Customer: 

CNIM SA

Introduction/challenge: 

As a result of modernisation and energy optimisation of the plant, the project was done in a short time within a very tight and detailed schedule.  

Solutions: 

We had to optimise electrical activities on site and organise adequate resources to complete the task.  

Scope of design:  

  • electrical design of LV switchgears  
  • engineering of LV busbars routing between MV/LV transformers and LV switchgears  
  • selectivity study  
  • engineering of IO cabinets  
  • engineering of local control boxes and safety switches  
  • engineering of UPS system  
  • harmonic distortion study 

Other projects

Customer: 

CNIM SA  

Introduction/challenge: 

The project was executed in 2 phases: 1. phase included preliminary design to obtain the building permit, we had very little input data at hand; 2. phase included detailed design for construction.  

Solutions: 

All documentation prepared was successfully approved and the permit granted solely thanks to the  experience and expertise of our designers.     

Scope of design:  

  • preparation complete package of technical specification for installation materials including applicable standard for: cables, cable ladders, conduits, accessories, junction boxes, labels  
  • design of cable trays in 3D and 2D including design of supplementary steel structures 
  • preparation of power, I&C, communication, and earthing cable schedules 
  • design of false floor including detailed design of supporting arms and collisions with cable ladders  
  • short circuit calculation notes  
  • typical wiring diagrams for switchgears, I/O cabinets and specific cubicles  
  • preparation of terminal wiring diagrams  
  • as-built documentation 

Customer: 

CNIM SA  

Introduction/challenge:   

A very detailed design was required to optimise the time schedule, site activities and material logistics.     

Solutions:   

A completed detail design study was performed including 3D design false floors, bend radius cable simulation, supporting structures for cable routes and detailed BOQ.    

Scope of design:  

  • monitoring and reporting tools for site activities: cable route installations, cable pulling, terminations, equipment installation, motor and cable tests, etc.)  
  • technical specification for installation materials including applicable standards for: cables, cable ladders, conduits, accessories, junction boxes, labels  
  • design of 3D cable routes including cable pulling cards   
  • 3D cable simulation (bend radius) and review of main motors terminal boxes compatibilities including specifications and BOQ of requested extension boxes 
  • 3D typical drawing of cables ways supports including the calculation notes and BOQ 
  • preparation of power, I&C, communication, and earthing cable schedules  
  • design of false floor including detailed design of supporting arms and collisions with cable ladders  
  • cables drum specification for purchasing  
  • detailed bill of materials for glanding, cable lugs, cable ties, etc.  
  • terminal wiring diagrams   
  • as-built documentation  
  • site supervision during cable tray and cable installation
contact_icon
Enetecs
engineering technologies

VAT No 6832105801
KRS 0000791839
REGON 383681032

Enetecs sp. z o.o. is registered in the District Court for Kraków Śródmieście, XII Commercial Division, share capital: PLN 5.000

PLN 88 1050 1445 1000 0090 3218 0524
EUR 66 1050 1445 1000 0090 3218 0532
GBP 32 1050 1445 1000 0090 8090 0849
SWIFT/BIC INGBPLPW

contact form